|
Federal Regulations, Codes, &
Standards Users Group © |
|
||
|
|
|||
|
ASME |
|||
|
|
|||
|
Introduction Prepared By: Ron Lippy Company: True North Consulting Meeting Dates: November 28 – December 1, 2005 Meeting Location: Meeting Notes ISTA---General Requirements
ISTC---Valves 1.
Revise
Categories of Valves (Cat A vs. Cat AC)—Recent regulatory inquiries regarding
the determination of Cat A and AC valves.
Will be evaluated prior to next OM Code meeting (July 2006).—V-96-03 2.
Rapid Acting
Valves, Stroke Testing of 2-4 second valves.
V-02-01---CLOSED. No Action Taken. 3.
Incorporation
of OMN-1 into ISTC. V-97-01. OMN-1 Revision 1 should go for ballot NLT
January 2006. Once Approved—then to 4.
Appendix I and
ADS valve test schemes is working. 5.
OMN-8 is being
revised for applicability and being incorporated into OM Code,
ISTC-5100. OMN-8 should be approved by
ASME in early 2006. Should be in 2006 addenda. 6.
Inquiry
V05-01C—Inquiry on “test interval” being the frequency of testing for the
CV. For example, if the CV is forward
tested in RFO, then the reverse testing must be performed during the RFO. 7.
Inquiry: a.
Code edition:
ASME/ANSI OM-1987/1988a, Part 10 through the OM Code 2001 Edition OMb 2003 Addenda. Question: Is it a requirement of Table ISTC-3500-1
(Table 1) and applicable sections of ISTC-3630 (para.
4.2.2.3), that Category A valves (other than CIVs),
be individually leak tested? Response: No {Reference ISTC-3630(e), ISTC-3630(f)}. ISTB---Pumps 1.
OMN-6,
Revision 1, 2.
OMN-6 should
be incorporated into 2006 addenda of OM Code. 3.
Revision to
ISTB-6200 to provide clarification for use of Alert Range Analysis
Requirements. Should be approved 2006.
(P00-02) 4.
OMN-9, Code
case for use of pump curves being revised for “applicability (and to resolve
NRC concerns regarding the required measurements). Should be approved in 2006. 5.
P98-06,
regarding changes to Inaccessible upper motor bearing housings (Question
3.4.4 Workshop Summary). Awaiting
comments from NRC. May 2006. 3.4.4* Could the fact that the upper motor bearing housing is
not accessible on many vertical shaft pumps be addressed on a generic basis,
so a relief request would not be necessary? If this issue is a generic concern, the Code committees could
consider revising the Code to address these pumps. As discussed previously, the staff has no
plans to supplement GL 89-04 to provide generic relief. Specific relief has been granted from the
Code vibration requirements where access to the upper motor bearing housing
is inaccessible (e.g., Hatch Safety Evaluation dated 6.
P98-03,
regarding instrumentation test failures (Question 3.3.1 Workshop
Summary). Closed. No Code change
required. 3.3.1* If a pump fails a test, and it is obvious that the
failure was due to an instrument problem, can the pump be declared operable
when the failed instrument is identified? What is the Code requirement
regarding the time allowed for retest when the instruments involved are
recalibrated? The pump may be declared operable,
provided that it is clear the failed instrument is the overwhelming cause of
the failed test. The failed instrument
should be recalibrated, and data promptly taken with the new equipment. There
is no Code requirement for the timing of the retest, beyond satisfying the
pump surveillance interval. However,
the licensee should redo the test promptly to verify that the cause was
indeed the instrumentation. If the
cause of anomalous data cannot clearly be attributed to the malfunctioning
gauge, then it should be attributed to pump failure. The licensee would then declare the pump
inoperable and evaluate the condition of the pump in accordance with the
applicable technical specification. See
NUREG-1482, Appendix A, Question Group 45 and 46. 7.
P00-04,
regarding Temporary Reference Values and Repair, Replacement and Maintenance
of Pumps. In particular, can you use a
Group A Pump Test in lieu of a Comprehensive Pump test, when a Group B pump
has had “major maintenance” which could affect the Hydraulic Profile of the
pump, return the pump to operability, in part based on the results of the
“mini-flow” test, and then perform a Comprehensive Pump test as soon as
practicable? - this was CLOSED without any further action being taken. 8.
Pump Design
Flow Rate, being redefined as Comprehensive Pump Test Flow Rate
(P03-02). Still NOT fully
acceptable. Working. 9.
Comprehensive
Pump Test Substitution, regarding the use of a Group A test in lieu of CPT,
using ONLY installed instruments (provided that the instruments satisfy the
IST requirements for 2% tolerance and 3 times ref value or less for
Range. The proposal is to permit the
pressure instruments for CPT to continue to use the instrument tolerance of
+/- 2% in lieu of the requirement to use instrument tolerance of +/- 0.5% for
pressure instruments. To change the
103% upper limit for the pump acceptance criteria from “required action” to
“alert”, implement the more restrictive acceptance criteria for the lower
limits (Alert and Required Action).—ROM 04-04. Appendix I---Safety and Relief Valves 1.
Adele Dibiasio has resigned from Appendix I Subgroup. Shawn Comstock to be Chairman of Appendix
I. 2.
Frank Cherney resigned from Appendix I (NRC) to be replaced by
Mr. Gary Hammer. 3.
Inquiry
OMI-05-01, regarding testing 1 RV in a group every 10 years. No.
Code requires 20% every 48 months. 4.
Code Cases
OMN-2, 5, and 14 being incorporated into OM Code and will be allowed to
“expire”. 5.
Extension of
RV testing greater than 5/10 years for Class 1/Class 2 & 3 RVs. Maintenance requirements will be added to
Appendix I which will permit this. OM-8---MOVs 1.
Working on issuing
OMN-1 and then incorporating OMN-1 into ISTC as Appendix III. 2.
7 sites
currently implementing OMN-1, Revision 0. 3.
18 sites
pending for implementation of OMN-1, Revision 1. OM-19---AOVs 1.
Code Case
OMN-12 being submitted for Comments.—December 2005. 2.
Code Case to
be incorporated into OM Code as Appendix IV.
2007? ISTD---Snubbers 1.
Preparation
for approval of Code Cases OMN-10, Revision 1. 2.
Discussion on
“promotion” of the use of the ISTD and Code Cases for snubber
testing. NRC exhibited “favourable” position of stations using ISTD and Code
Cases, in lieu of Technical Specifications. ISTE---RI-IST 1.
Essentially
ISTE will become a new subsection of the Code. ISTE essentially will provide a “pointer”
to the Code Cases (Appendices) regarding RI-IST methodology, as the sections
and Code Cases are approved and endorsed by the NRC. ISTE is being submitted for Comment. 2005? 2.
Based upon
comments received will probably be incorporated into 2007 edition of the OM
Code. OM-22---Check Valves 1.
Discussions
regarding disassembly and Inspection of CVs during Power Ops. Primarily now, NRC “encourages” the use of
CV Condition Monitoring for the “online D&I”. 2.
CV CMP
guidance on using “historical data”.
Some confusion exists as to if and when you can use “existing” historical
CV data to implement the Appendix II CV Condition Monitoring. This would be a “clarification” of the Code. Liasons---NRC 1.
Gene Imbro has been promoted to Deputy Chief of Engineering
Component Integrity. 2.
Dr. Sam Lee
has been assigned as Component Test Group Head (taking Gene’s place). 3.
Discussion on
converting NUREG 1482, Revision 1 to a Regulatory Guide. More Regulatory “footprint”. 4.
Discussion on
“removing” RIS-2004-012 requirements regarding use of later Code
editions/addenda. Pending NRC
evaluation of “benefit” or “value added”.. 5.
SRP 3.9.6
(IST) to be revised in 2006. 6.
10 CFR 50.69
Approved. 7.
Look to
approve OM Code 2004 addenda in September 2006? 8.
RG 1.193 Rev.
1 issued in October 2005. RG 1.192
will be revised on an “as required” basis.
When Code Cases have been revised or changes to “applicability” have
been made and approved by ASME…and Included in the revised ASME OM Codes. Pump Performance Group 1.
Looking at moving
pump testing to 6 months using more “comprehensive tests/exams (e.g. oil analyses,
spectral analysis for vibration). 2.
Various
discussions on pump performance testing which will eventually be incorporated
into the Code (ISTB). RISC 3 Group
Miscellaneous 1.
Discussion on
incorporating Appendix J requirements into OM Code, as a standard to the OM
Code. Discussions ensued
involving ANSI reaction. 2.
Inquiry into
the correctness of the formula used for OM-24 standard: "Please validate the accuracy of the following equation
contained within ASME
OMb‑S/G‑2005 Addenda to ASME OM‑S/G‑2003, Part
24 "Reactor Coolant and Recirculation Pump
Condition Monitoring", Section
9.2 "Determining 1x and 2x Vector
Acceptance Regions", Subsection
9.2.4: Accept = 1/2 *(max.+ min.) +/‑ 1.5 / (max.‑ min.) Accept
= 1/2 *(max.+ min.) +/‑ 1.5*(max.‑ min.) Note
the difference after the +/‑ signs => ASME divides, the utility multiplies! Response: The correct formula is Accept
= 1/2 *(max.+ min.) +/‑ 1.5 * (max.‑
min.) This
method has worked very well. We have
also determined that if the amplitude
acceptance regions is close to zero, or if the phase acceptance
region is 330 degrees or more, we will disable the phase monitoring. Our
process also allows us to adjust the parameters based on engineering judgment.
For example we may turn off the phase region monitoring
based on an evaluation of the data, or we may decide to ignore certain extreme values. 3. Discussion regarding adoption of ASME/OM
Codes in the world ( 4. Next OM Code meeting in July 2006 following
Pump and Valve Symposium in 5. Winter Code meeting to be in 6. ASME NRC 9th Pump and Valve
Symposium, to be held in |
|||
|
|
|||
|
|
|||